Tier III Data Center Power Infrastructure Refresh

Replaced end-of-life UPS systems and optimized power distribution with zero downtime.

Outcomes

  • Achieved 25% increase in energy efficiency (PUE improvement)
  • Eliminated single points of failure in power delivery
  • Zero-downtime migration completed during peak trading hours

Challenge

Aging power infrastructure, high risk of failure, and lack of modular scalability for high-density racks.

What we did

Audit → Load bank testing → Parallel UPS installation → Live cutover → Thermal mapping.

Result

A redundant, energy-efficient power backbone capable of supporting 5 years of projected growth.